PlumbRevise
All field toolsField tool

Gas Pipe Sizing Calculator

Work out the design load, gas volume and route length you need before a BS 6891 pipe-size table lookup.

Gas Pipe Sizing Pre-Check

Load, gas volume and route worksheet before the BS 6891 table lookup.

Total design load31 kW
Required gas volume2.83 m³/h
Planning run to check14.4 m
Added route allowance2.4 m
Final diameterUse BS 6891 table lookup

Method: BS 6891 (gas pipework design)

How it works

Gas pipe sizing starts with the load carried by each pipe section. A section feeding more than one appliance carries the combined rated heat input of all appliances downstream of that section.

The calculator converts total heat input into required gas volume using the same energy relationship as gas rating: required gas volume (m³/h) = heat input (kW) × 3.6 ÷ calorific value (MJ/m³).

Route length is not just the tape-measured straight run. Bends, tees, valves and other fittings add resistance. This worksheet lets you add a planning allowance so you can revise the process, but the real equivalent lengths and final diameter come from the current BS 6891 tables, manufacturer data and the actual route.

Do not use this page as a permission slip to install or alter gas pipework. It is a revision and pre-check tool: final pipe size, pressure-loss proof, tightness testing and commissioning belong to competent registered gas work.

Worked example

A 24 kW boiler and 7 kW cooker on the same upstream section give 31 kW total design load. At CV 39.5, required gas volume = 31 × 3.6 ÷ 39.5 ≈ 2.83 m³/h. A 12 m straight route with a 20% planning allowance gives 14.4 m to take into the BS 6891 sizing check.

Printable gas pipe sizing worksheet

Use this as a revision checklist before the actual standard-table lookup. It records the inputs that decide the pipe section, not a copied pipe-size table.

Worksheet lineRecordWhy it matters
Appliances downstreamEvery appliance fed by the sectionShared pipework carries combined load
Rated heat inputkW for each applianceSets the design gas flow
Fuel and CVNatural gas, LPG or supplied CVConverts kW into m³/h
Route lengthStraight run plus real fittingsPressure loss rises with length and resistance
Candidate material/diameterCopper, steel, CSST or other approved systemTables and manufacturer data are material-specific
Commissioning proofWorking pressure, tightness and appliance checksA table result still needs live verification

For live work, replace the planning allowance with the actual fitting equivalents and current standard/manufacturer data. This worksheet intentionally does not select a pipe diameter.

Gas pipe sizing questions

What size gas pipe do I need for a 30 kW boiler?

There is no single answer from kW alone. You need the total load on each pipe section, gas type, route length, fittings, pipe material, meter/regulator context and the current BS 6891 sizing method.

How far can you run 22 mm gas pipe?

It depends on the load, route, fittings and pressure-loss allowance. A short 22 mm run may be fine in one design and wrong in another, so the answer has to come from the standard-table lookup and commissioning checks.

What happens if gas pipework is undersized?

The appliance can be starved of gas under full demand, giving poor operation, lockouts, incomplete commissioning or unsafe results that need risk assessment and correction.

Can gas pipework be oversized?

Oversizing is usually a design, cost, routing and support issue rather than the same immediate starvation problem as undersizing, but the installation still has to meet the standard, be supported and be proved sound.

Method: BS 6891 (gas pipework design)

Training & revision aids — live installations follow the full standard, the manufacturer’s instructions and calibrated instruments.