Boiler commissioning: order of work

Checklist · Note 8 of 27 · free to read

The commissioning order: prove the gas sound and the system clean before firing, then check pressure, gas rate, combustion and flue, and hand over.

Commissioning establishes safe operation and the specified performance before handover. Complete the required gas-soundness and pre-firing checks before lighting the boiler. The stages below are a framework: follow the exact appliance procedure, including any permitted heated cleaning cycle and repeated filling, rinsing or treatment stages. Protect a new appliance from contamination in existing pipework.

  1. Prove the gas work is sound. Select the tightness-test boundary and connection checks for what was installed or disturbed. New or altered installation pipework requires the applicable installation test; new pipework must show no perceptible pressure loss. An appliance-only connection has its appropriate soundness check. Complete the required checks and purging before firing.
  2. Plan and carry out cleaning. Remove debris, flux and swarf using the specified procedure. Existing circuits should be cleaned before exposing a new appliance to their contamination. Some manufacturers permit a new boiler to assist cleaning a newly installed system, with specified protection; complete the required safety checks before any such firing. Remove the cleaner and debris before establishing the final inhibitor dose.
  3. Fill and check. Establish the required water content, vent air, check for leaks and set the specified cold pressure on a sealed system before operation. Repeat the relevant checks after any cleaning drain-down and refill.
  4. Fill the condensate trap, so its water seal stops flue gases escaping from the condensate outlet.
  5. Check before firing. Confirm the electrics and controls are safe and the flue is correctly assembled and suitable. Complete the model’s pre-firing flue checks, including the flue-flow test where required for an open-flued appliance.
  6. Check the supply under load. Bring the boiler to the maker’s prescribed maximum test condition. With the other connected gas appliances also operating, read the pressure at its inlet and compare it with that model’s limits. A standing reading can look normal even though the pressure drops when everything runs at once. Record the test conditions and investigate an out-of-range result before continuing. This check does not tell you the gas rate or whether the installation is tight.
  7. Check the gas rate. With other gas use excluded, time the meter in the maker's specified high-rate mode. Volume divided by elapsed time gives m³/h; compare it with a stated gas-rate figure at the same operating point. To compare with heat input in kW, multiply m³/h by the fuel's calorific value in MJ/m³ and divide by 3.6, then match gross with gross or net with net. Check burner pressure where this model's instructions specify a target; do not assume every modern boiler has one or adjust its gas valve by guesswork. For an unexpectedly high rate, investigate the model-specific supply and set-up. For a low rate after the reading has stabilised, check working inlet pressure and possible pipework restriction before blaming the boiler.
  8. Check running flue integrity and combustion in the maker's order. Complete any prescribed air-intake/flue-integrity check before interpreting combustion readings where the model requires it. For example, the Greenstar 8000 Life checks an air-intake sample first, with its combustion casing fitted, before using the separate flue-gas sample point. Analyse combustion with a suitable calibrated instrument after readings settle, at each specified output (often maximum and minimum). Compare CO, CO2 and the CO/CO2 ratio with that model's limits. A good result at one operating point says nothing about another. Refit sample-point plugs as instructed.
  9. Finish the remaining flue checks. Confirm the room-sealed case and flue seals are sound and correctly fitted using the specified checks. On an open-flued appliance, carry out the spillage test at the stated operating conditions; this is separate from the earlier flue-flow check. Persistent spillage after the prescribed further running and repeat test prevents completion of commissioning. If the cause cannot be corrected, disconnect and seal the gas supply, label the appliance against use and tell the responsible person. Complete commissioning before it returns to service.
  10. Finish treatment and prove operation. Complete any specified final flush, establish the inhibitor dose, and check the filled and vented system. Prove the controls and safety devices, including the interlock, then balance emitters to their design duties using the fitted adjustment devices.
  11. Hand over. Leave the completed commissioning record and the manufacturer's instructions with the user. Give building control the commissioning notice within the period for the notification route used. England's Approved Document L 2021 allows up to 30 days after completion for the competent person scheme route, and five days where a building notice or full plans went to the local authority. Being a scheme member does not decide which route applies.

Establish the correct test mode

For the Ideal Logic+ Combi2 C24/C30/C35 (October 2023), measure the meter gas rate at full domestic hot-water output, with other gas appliances out of use. The maximum-DHW-rate programme runs for ten minutes provided enough cooling load is available. The flowing water must remove the heat; a high thermostat setting or a normal static pressure does not provide that.

Its minimum-rate programme has a deliberate start-up sequence. With return water below 40 °C, the fan first runs at maximum for 30 seconds, then takes 60 seconds to ramp down. Above 40 °C it ramps down over 60 seconds without that initial high-speed period. Let the specified condition settle before interpreting a minimum-rate combustion sample; a fan that starts fast on a cold return has not failed the test command.

The 2021 ecoTEC plus VU/VUW ..6/5-5 uses different check programmes:

  • P.00 cycles the pump to remove air from the water circuits. Keep the automatic air-vent cap loose as instructed. This is water-system venting, not purging a gas pipe.
  • P.06 moves the diverter valve to its mid-position for filling or draining, with the pump and burner switched off.
  • P.01 and P.02 provide maximum and minimum heat input respectively for the relevant operating checks. They do not replace the water filling and venting programmes.

Use the programme for the task and the appliance. The same code on another boiler may do something different.

Check service access before accepting the installation

A boiler that fits inside a cupboard must still leave room for the work its manufacturer requires. Use the model's dimensions, and check what space becomes available when a door or panel is opened.

For the Ideal Logic+ Combi2 C24/C30/C35 (October 2023), a closed cupboard door may leave only 5 mm in front, but opening it must provide 450 mm for servicing. Beneath the boiler, the required 100 mm may reduce to 15 mm after installation only with an easily removable panel that restores the full servicing space. A fixed obstruction under the boiler does not provide that access.

For the ecoTEC plus VU/VUW ..6/5-5 in Vaillant's 2021 manual, leave 500 mm in front for maintenance; an opening door may provide it. The top clearance is 165 mm with a 60/100 mm air/flue pipe, or 275 mm with an 80/125 mm pipe. The minimum below is 180 mm, with about 250 mm preferred. Each side needs 5 mm minimum; about 50 mm is the suggested optimum. The optimum is useful working space, not another minimum. Once the specified clearances are met, this manual calls for no extra distance from combustible components, owing to the casing's low heat loss.

When fitting that Vaillant model's seals, the permitted aids are water or commercially available soft soap. Grease and other lubricants are not allowed, and not every detergent is soft soap. Refit the seals and casing as specified, then complete the required integrity checks.

Common mistakes

  • Dosing inhibitor before flushing, so it washes out with the debris.
  • Reading the gas rate with the boiler modulated down, which understates it.
  • Condemning a boiler for a low gas rate before checking supply pressure and pipework.

Why each check matters

  • Rate, combustion and flue integrity answer different questions. Meter timing gives volume flow; applying the appropriate calorific value gives fuel heat input. Flue-gas samples let you judge combustion at the tested settings; they tell you nothing about whether the installation pipework is tight or every flue joint and case seal is sound. Complete the separate checks in the model's commissioning sequence. A correct heat input cannot excuse poor combustion, and an acceptable combustion sample cannot excuse an excessive gas rate.
  • Flushing and inhibitor. Flux, swarf and sludge left in the water can damage the new heat exchanger and cut its efficiency, and the inhibitor then protects the clean system against corrosion and scale, so one never replaces the other. England’s Approved Document L calls for cleaning and flushing the existing circuits before a new heating appliance is installed and for suitable inhibitor in the primary circuit. Follow the model’s permitted cleaning sequence and add the final protective dose after the cleaner has been removed.
  • Case seal. Where a boiler casing forms part of the combustion circuit, its seal keeps that circuit separate from the room. A perished, damaged or badly refitted seal can let products of combustion escape; a decorative cover may have a different role. Whenever the casing comes off, check the seals, renew any that are cracked, hardened or damaged, and refit the casing exactly as the instructions show. Evidence of escaping combustion products requires immediate safety action and assessment under the unsafe-situations procedure; confirmed leakage or spillage from a flued appliance is an Immediately Dangerous situation.
  • Manufacturer's instructions. They give the safe set-up for that model, including its gas rate and combustion figures and the flue components and lengths it may use. They apply alongside the Gas Safety Regulations, never in place of them. Leaving them with the user is a legal duty under regulation 29 of the Gas Safety (Installation and Use) Regulations 1998, and the completed commissioning record gives the next engineer readings to compare against.
  • Hard water. In hard water areas, Approved Document L asks for the feed to water heaters and to a combi's hot water circuit to be treated to reduce limescale. Inhibitor belongs only in the sealed heating circuit, never in the water drawn at the taps.
  • Softened water. Where a salt-based softener serves the property, follow the boiler maker's water rules. The Greenstar 8000 Life instructions, for example, call for inhibitor and a heating-water pH of 6.5 to 8.0 at commissioning; if the filling point has no permanent untreated supply, the pH is checked every year and written in the service record.