The operational checks and documentation needed to bring a hot water system into safe service.
Bringing the system into service
Commissioning is the controlled process of proving a hot water system is safe and working before handover. Work to a sequence and to the manufacturer instructions.
Typical operational checks
- Clean and fill. Flush out debris, fill the system, and vent trapped air from the cylinder and pipework.
- Leak check. Inspect joints and fittings under pressure before applying heat.
- Energise and set temperature. Only apply heat after the required filling, venting and safety checks. Set and measure the temperatures specified for the design and hygiene-control regime, normally at least 60 °C for conventional hot-water storage.
- Prove the safety devices. Check the controls, specified safety responses and clear discharge route using the manufacturer procedure. Verify the actual expansion arrangement: an external vessel needs its specified charge and condition checked, while an internal-air design has its own checks. Some unvented cylinders have no external vessel.
- Check delivery. Check the unblended hot supply and the separate blended outlet temperatures at TMVs. For a new dwelling in England the bath ceiling is 48 °C; vulnerable users may need lower limits. Prove the specified cold-supply-failure response.
Records and documentation
Good commissioning is written down. Record the thermostat setting, measured temperatures, relief valve and expansion checks, and any TMV set points, then complete the commissioning or benchmark logbook and leave it with the user. Confirm the applicable building-control notification route and any exemption for the installation. A commissioning record does not replace a required notification. Keep a copy on file. Always follow the current standard for the appliance and the manufacturer commissioning sheet.
Balancing and timing checks
Balance a secondary circulation loop at commissioning and confirm the pump drives water round the intended flow path. For the conventional temperature regime, check the unblended hot supply for at least 50 °C within one minute, or 55 °C in healthcare premises. At a short outlet spur close to a circulating return, expect the required hot temperature in under 30 seconds. Check a TMV’s blended delivery separately against its scald-control limit. A slower result needs investigation, and not only of the pump: check the actual temperatures, draw-off flow, branch volume and local circulation.