Handover and Commissioning Records

Note 15 of 17 · free preview · full note on Premium

Completing records and instructing the customer so the system is compliant, warranted and understood.

Records to complete

A professional handover is more than turning the system on. Complete and leave:

  • The Benchmark commissioning checklist, completed with the actual checks and results. It supports the commissioning record; warranty cover also depends on the manufacturer’s terms, registration and servicing requirements.
  • The Building Regulations compliance paperwork for the work, notified through the correct route.
  • Manufacturer registration of the appliance warranty.
  • The water-treatment record (cleaner and inhibitor used).
  • Balancing and lockshield settings, and the design flow temperature and heat-loss figures the system was sized to, so a later fault, alteration or high bill can be checked and design flow restored rather than guessed.